[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384377":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384377,165,1,"单选题","某大型信息系统集成项目组建了一个变更控制委员会来负责项目变更请求的审查与处理工作，并且确立了支配其运作的具体程序和规则。这个程序要求所有得到批准的变更都必须反映到 （ ） 中。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业绩衡量基准",false,{"key":16,"text":17,"correct":14},"B","变更管理计划",{"key":19,"text":20,"correct":21},"C","质量管理计划",true,{"key":23,"text":24,"correct":14},"D","质量保证计划","变更管理计划记述了变更流程和变更控制委员会的内容。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]