[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384367,165,1,"单选题","整体变更控制过程实际上是对 （） 的变更进行标识、文档化、批准或拒绝，并控制的过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","详细的WBS计划",false,{"key":16,"text":17,"correct":18},"B","项目基准",true,{"key":20,"text":21,"correct":14},"C","项目预算",{"key":23,"text":24,"correct":14},"D","明确的项目组织结构","本题考查项目变更控制。 《系统集成项目管理工程师教程》的“整体变更控制”节指出：项目变更就是对被批准的项目管理计划的变更，而被批准的项目管理计划就是项目基准。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]