[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384352,165,1,"单选题","项目承建方在投标前一般也需要进行项目论证，主要是从技术可行性、人力及其他资源可行性、财务可行性、（）。以及对其他参与竞争投标方情况分析等方面进行论证。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目风险分析",true,{"key":16,"text":17,"correct":18},"B","项目的社会影响分析",false,{"key":20,"text":21,"correct":18},"C","项目的国民经济分析",{"key":23,"text":24,"correct":18},"D","项目的运行环境分析","项目承建方在投标前一般也需要进行项目论证，主要是从技术可行性、人力及其他资源可行性、财务可行性、项目风险分析以及对其他参与竞争投标方情况分析等方面进行论证。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]