[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384345":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384345,165,1,"单选题","承建方在进行项目论证时，论证的内容不包括 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承建方技术的可行性分析",false,{"key":16,"text":17,"correct":14},"B","承建方人力及其他资源配置能力可行性分析",{"key":19,"text":20,"correct":14},"C","项目财务可行性分析",{"key":22,"text":23,"correct":24},"D","项目国民经济评价分析",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]