[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384344,165,1,"单选题","某系统集成商准备去投标一个政府网站开发项目，该系统集成商 在项目招投标阶段的工作依次是( )。 ①组建评标小组 ②编制投标文件中 ③参写开标过程 ④研读招标公 告 ⑤提交投标文件",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①②③④⑤",false,{"key":16,"text":17,"correct":14},"B","⑤②④③",{"key":19,"text":20,"correct":21},"C","④②⑤③",true,{"key":23,"text":24,"correct":14},"D","①④⑤②③","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]