[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384337":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384337,165,1,"单选题","建设方在进行项目评估的时候，根据项目的类型不同，所采用的评估方法也不同。如果使用总量评估法，其难点是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","如何准确确定新增投入资金的经济效果",false,{"key":16,"text":17,"correct":18},"B","确定原有固定资产重估值",true,{"key":20,"text":21,"correct":14},"C","评价追加投资的经济效果",{"key":23,"text":24,"correct":14},"D","确定原有固定资产对项目的影响","总量评估法的费用、效益测算采用总量数据和指标，确定原有固定资产重估值是估算总投资的难点。该法简单，易被人接受，侧重经济效果的整体评估，但无法准确回答新增投资的经济效果。例如，针对一个小炼钢厂，需要作出是进一步进行技术改造还是关、停、并、转的决策。该项目需要从整体上把握经济效益的变化和能够达到的经济效益指标。此时，应该采用总量法。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]