[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384333,165,1,"单选题","乙公司参加一个网络项目的投标，为增加中标的可能性，乙公司决定将招标文件中的一些次要项目（约占总金额的3%）作为可选项目，没有计算到投标总价中，而是另作为一张可选价格表，由招标方选择是否需要，评标时，评委未计算可选价格部分，这样乙公司因报价低而中标。洽谈合同时，甲方提出乙方所说的可选项目是必需的，在招标文件中已明确说明，要求乙方免费完成，乙方以投标文件中有说明为由不同意免费，该项目最可能的结果是 （ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","甲方追加经费",false,{"key":16,"text":17,"correct":18},"B","重新招标",true,{"key":20,"text":21,"correct":14},"C","甲方不追加经费，相应部分取消",{"key":23,"text":24,"correct":14},"D","重新确定中标方","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]