[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384329":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384329,165,1,"单选题","在利用招标方式选定项目承建方过程中，下列做法错误的是 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","中标人应最大限度地满足招标文件中规定的各项综合评价标准",false,{"key":16,"text":17,"correct":14},"B","招标人可以授权评标委员会直接确定中标人",{"key":19,"text":20,"correct":14},"C","中标人确定以后，招标人应向中标人发出中标通知书",{"key":22,"text":23,"correct":24},"D","招标人和中标人应当自中标通知书发出之日起15日内，订立书面合同",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]