[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384294":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384294,165,1,"单选题","某单位为加强项目管理，计划在 2013 年建设一个项目管理系统，但企业领导对该系统没有提出具体要求。钱工是项目负责人，要对项目的技术、经济等进行深入研究和方案论证，应 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进行项目识别",false,{"key":16,"text":17,"correct":14},"B","编制项目建议书",{"key":19,"text":20,"correct":21},"C","编制可行性研究报告",true,{"key":23,"text":24,"correct":14},"D","聘请评估机构对项目进行评估","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]