[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384293":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384293,165,1,"单选题","项目建议书应该包括的核心内容可不包括 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目建设必需的条件",false,{"key":16,"text":17,"correct":14},"B","项目的必要性",{"key":19,"text":20,"correct":21},"C","项目的风险预测及应对措施",true,{"key":23,"text":24,"correct":14},"D","产品方案或服务的市场预测","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]