[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384281":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384281,165,1,"单选题","项目团队测量其执行风险响应计划的有效性是基于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","风险接受的阈值",true,{"key":16,"text":17,"correct":18},"B","风险得分",false,{"key":20,"text":21,"correct":18},"C","可能性\u002F冲击风险评价",{"key":23,"text":24,"correct":18},"D","项目总的风险级别","风险管理计划应该讨论阈值判据，确定什么时候处理风险、谁来处理和处理的方法。项目拥有者、客户或发起人可能有不同的风险阈值。接受的阈值是一个目标，据此项目团队将测量风险响应计划执行的有效性",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]