[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384274,165,1,"单选题","李工是一个投资300万的产品开发项目的项目经理。项目已经进入执行阶段，时间，预算和规范方面都符合要求。某天，一名项目团队成员就报纸的一篇报道提醒李工注意。该报道详细说明了产品原型中使用的材料存在非常高的缺陷率。在此之前，李工对材料的质量没有产生过任何怀疑。此时，李工应该采取的第一项措施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","停止原型工作",false,{"key":16,"text":17,"correct":18},"B","对风险进行量化",true,{"key":20,"text":21,"correct":14},"C","制定风险缓解计划",{"key":23,"text":24,"correct":14},"D","确定权变措施","出现风险，首先应先分析。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]