[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384247":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384247,165,1,"单选题","某大型项目的变更策略规定：把变更分为重大、紧急、一般和标准变更，并规定了不同级别的审批权限，比如重大变更由CCB审批，并规定标准变更属于预授权变更，可不用再走审批流程。此项目变更策略（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可行",false,{"key":16,"text":17,"correct":14},"B","不可行，主要是变更不能分级别，应统一管理",{"key":19,"text":20,"correct":14},"C","不可行，分四级可以，但审批都应由CCB批准",{"key":22,"text":23,"correct":24},"D","不可行，标准变更规定有问题",true,"用排除法。变更都必须审批。但不一定全部由CCB批准。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]