[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384246":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384246,165,1,"单选题","配置控制与变更包含着几个重要的任务，变更申请，变更评估，通报评估结果，变更实施，变更验证，与确认，变更发布等。其中变更实施的主要负责人一般是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","CCB",false,{"key":16,"text":17,"correct":18},"B","项目经理",true,{"key":20,"text":21,"correct":14},"C","配置管理员",{"key":23,"text":24,"correct":14},"D","QA","CCB主要负责决策，具体的实施由项目经理负责。 变更实施：项目经理组织修改相关的配置项，并在相应的文档或程序代码中记录变更信息。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]