[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384243":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384243,165,1,"单选题","项目经理在综合变更中主要负责（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","评估变更对项目的影响",true,{"key":16,"text":17,"correct":18},"B","评估变更的应对方案",false,{"key":20,"text":21,"correct":18},"C","将变更由技术要求转换为资源要求",{"key":23,"text":24,"correct":18},"D","批准可否使用储备资源","项目经理在变更中的作用是：响应变更提出者的要求，评估变更对项目的影响及应对方案，将要求由技术要求转化为资源要求，供授权人决策；并根据评审结果实施即调整项目基准，确保项目基准放映项目实施情况。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]