[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384237":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384237,165,1,"单选题","下列关于需求变更工作程序说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","变更影响分析由项目经理负责，项目经理可以自己或指定人员完成，也可以召集相关人员讨论完成。",false,{"key":16,"text":17,"correct":14},"B","变更申请人提交的每个变更申请都必须由一位责任人批准或否决，这个责任人通常是项目发起人或项目经理。",{"key":19,"text":20,"correct":14},"C","项目经理负责整合变更所需资源，合理安排变更，对于不同的变更申请，涉及到的变更实施人员也不同。",{"key":22,"text":23,"correct":24},"D","变更申请被否决并通知项目管理变更申请人后变更结束。",true,"本题考查有关需求变更工作程序的相关内容。 变更申请被否决时变更结束，项目经理通知相关变更申请人。选项D没有先通知变更申请项目经理",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]