[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384229":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384229,165,1,"单选题","在项目配置项中有基线配置项和非基线配置项，（ ）一般属于非基线配置项。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","详细设计",false,{"key":16,"text":17,"correct":14},"B","概要设计",{"key":19,"text":20,"correct":21},"C","进度计划",true,{"key":23,"text":24,"correct":14},"D","源代码","配置项分为基线配置项和非基线配置项两类，基线配置项可能包括所有的设计文档和源程序等；非基线配置项可能包括项目的各类计划和报告等。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]