[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384228,165,1,"单选题","配置项目版本控制的步骤是（ ）。①技术评审或领导审批②正式发布③修改处于“草稿”状态的配置项④创建配置项",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①④③②",false,{"key":16,"text":17,"correct":14},"B","③②①④",{"key":19,"text":20,"correct":21},"C","④③①②",true,{"key":23,"text":24,"correct":14},"D","④③②①","配置项版本控制流程：创建配置项——修改处于“草稿”状态的配置项——技术评审或领导审批——正式发布——变更",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]