[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384188,165,1,"单选题","能够使建设单位在评标时易于报价最低的承包商，易于进行支付计算的合同是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工料合同",false,{"key":16,"text":17,"correct":14},"B","成本补偿合同",{"key":19,"text":20,"correct":21},"C","总价合同",true,{"key":23,"text":24,"correct":14},"D","分部分项合同","本题考查总价合同的特点。 总价合同能够使建设单位在评标时易于报价最低的承包商，易于进行支付计算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]