[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384171":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384171,165,1,"单选题","币值波动、政治动荡、中央和地方政府之间的竞争，以及不同利益集团之间的冲突可能会干扰国际项目的管理。管理国际项目的项目经理应该意识到跨文化环境的主要影响因素，并特别重视（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建立绩效报告制度",false,{"key":16,"text":17,"correct":18},"B","建立沟通管理系统",true,{"key":20,"text":21,"correct":14},"C","建立和执行生产进度表以方便信息分配，避免在定期会面之间出现情况的变化",{"key":23,"text":24,"correct":14},"D","通过翻译服务起草正式的项目报告","项目有关各方必须即使获得信息。通过沟通管理中的标准方式进行的全球范围的沟通可能会降低文化差异带来的影响。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]