[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384135,165,1,"单选题","虽然项目具有独特性，但考虑到当前进行的项目和去年已完工的一个项目类似，为了加快人力资源计划的编制，项目经理小王采用了这个类似项目的任务或职责定义、汇报关系、组织架构图和职位描述。小王在人力资源计划的编制过程中采用了（ ）方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织结构图和职位描述",false,{"key":16,"text":17,"correct":18},"B","人力资源模板",true,{"key":20,"text":21,"correct":14},"C","非正式的人际网络",{"key":23,"text":24,"correct":14},"D","活动资源估算","人力资源计划编制工具：人力资源模板虽然每个项目都是独一无二的，但大多数项目会在某种程度上与其他项目类似。运用一个以前类似项目的相应文档， 如任务或职责的定义、汇报关系、组织架构图和职位描述，能有助于减少疏漏重大职责，项目人力资源计划的编制。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]