[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384124,165,1,"单选题","质量控制输入中工作绩效数据不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实际技术性能",false,{"key":16,"text":17,"correct":14},"B","实际进度绩效",{"key":19,"text":20,"correct":21},"C","实际质量绩效",true,{"key":23,"text":24,"correct":14},"D","实际成本绩效","本题考查工作绩效数据内容。 工作绩效数据包括： （1）实际技术性能（与计划比较）； （2）实际进度绩效（与计划比较）； （3）实际成本绩效（与计划比较）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]