[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384118,165,1,"单选题","下列关于质量审计的说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量审计可确认未批准的变更请求的实施情况。",true,{"key":16,"text":17,"correct":18},"B","质量审计可以是事先安排，也可以随机进行。",false,{"key":20,"text":21,"correct":18},"C","质量审计的目标之一是识别全部正在实施的良好及最佳实践。",{"key":23,"text":24,"correct":18},"D","质量审计是对具体质量管理活动的结构性评审。","本题考查质量审计。 质量审计可确认已批准的变更请求的实施情况。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]