[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384117,165,1,"单选题","实施质量保证输出包括变更请求、项目管理计划更新、项目文件更新、组织过程资产更新，下列不属于项目管理计划更新的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量管理计划",false,{"key":16,"text":17,"correct":18},"B","成员管理计划",true,{"key":20,"text":21,"correct":14},"C","进度管理计划",{"key":23,"text":24,"correct":14},"D","成本管理计划","本题考查项目管理计划更新的内容。 项目管理计划更新的内容包括（但不限于）： （1）质量管理计划 （2）范围管理计划 （3）进度管理计划 （4）成本管理计划",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]