[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384107":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384107,165,1,"单选题","项目成本预算的特征不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","精确性",true,{"key":16,"text":17,"correct":18},"B","计划性",false,{"key":20,"text":21,"correct":18},"C","约束性",{"key":23,"text":24,"correct":18},"D","控制性","本题考查项目成本预算的特征。 项目成本预算的特征包括：计划性、约束性、控制性。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]