[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384105":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384105,165,1,"单选题","下列关于成本预算输出错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","A. WBS各组件的CV、SV、CPI、SOI、TCPI、VAC值，都需要记录下来，并传达给干系人。",false,{"key":16,"text":17,"correct":14},"B","无论是计算得出的EA还是自下而上估算的EAC值，都需要记录下来传达给干系人。",{"key":19,"text":20,"correct":14},"C","变更请求需经过实施整体变更控制的审查和处理。",{"key":22,"text":23,"correct":24},"D","项目管理计划中可能需要更新的内容包括成本基准和成本计划。",true,"本题考查项目成本控制的输出。 D项目中，项目管理计划中可能需要更新的内容包括成本基准和成本管理计划。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]