[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384104":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384104,165,1,"单选题","下面关于项目成本预算及作用正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本预算不能确定衡量项目绩效情况的总体成本基准",false,{"key":16,"text":17,"correct":14},"B","项目范围说明书没有提供汇总预算",{"key":19,"text":20,"correct":21},"C","成本预算是在项目成本估算基础上的",true,{"key":23,"text":24,"correct":14},"D","成本预算是将未批准的项目总的估算成本进行分摊","本题考查项目成本预算及作用。 A项成本预算能确定衡量项目绩效情况的总体成本基准；B项项目范围说明书提供了汇总预算；C项正确；D项成本预算是将已批准的项目总的估算成本进行分摊。故本题答案选择C。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]