[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384100":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384100,165,1,"单选题","项目管理计划应整合其他规划过程的所有子计划和基准，一经确定即成为项目的基准。在项目管理中通常将（ ）合并为一个绩效测量基准，这些基准可应用于挣值测量从而判断项目的整体绩效。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","范围基准、成本基准、进度基准",true,{"key":16,"text":17,"correct":18},"B","质量基准、成本基准、范围基准",false,{"key":20,"text":21,"correct":18},"C","质量基准、进度基准、范围基准",{"key":23,"text":24,"correct":18},"D","质量基准、进度基准、成本基准","挣值技术表现形式各异，是一种通用的绩效测量方法。它将项目范围、成本（或资源）、进度整合在一起，帮助项目管理团队评估项目绩效。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]