[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384096,165,1,"单选题","（ ）is aproject mangement technique for measuring project performance and proress.it has the ability to combine measurements of the project management triangle;scope.time and costs.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Critica path method（CPM）",false,{"key":16,"text":17,"correct":18},"B","Earned value mangagemengt（EVM）",true,{"key":20,"text":21,"correct":14},"C","Net present value method（NPVM）",{"key":23,"text":24,"correct":14},"D","Expert judgment method（EJM）","本题考查的是挣值的相关知识。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]