[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384091":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384091,165,1,"单选题","将项目总成本分摊到项目工作分解结构的各个工作包，分解应按照（ ），根据占用资源数量多少而设置不同的分解权重。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","自下向上",false,{"key":16,"text":17,"correct":14},"B","分部分项",{"key":19,"text":20,"correct":21},"C","自顶向下",true,{"key":23,"text":24,"correct":14},"D","由多到少","本题考查制订项目成本预算的步骤。 项目总成本分摊到项目工作分解结构的各个工作包，分解应按照自顶向下，根据占用资源数量多少而设置不同的分解权重。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]