[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384090":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384090,165,1,"单选题","在进行项目成本估算时，可以使用多种技术和工具，其中（ ）相对于其他估算技术来说，成本较低，耗时较少，但准确性也较低。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专家判断",false,{"key":16,"text":17,"correct":18},"B","类比估算",true,{"key":20,"text":21,"correct":14},"C","参数估算",{"key":23,"text":24,"correct":14},"D","三点估算","类比估算，是对以往的相类似的项目进行对比，进行估算项目成本，这个估算比较粗略，准确性较低",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]