[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384088":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384088,165,1,"单选题","项目进行到某阶段时，项目经理进行了绩效分析，计算出CPI值为0.91。这表示（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目的每91元人民币投资中可创造相当于100元的价值",false,{"key":16,"text":17,"correct":14},"B","当项目完成时将会花费投资额的91％",{"key":19,"text":20,"correct":14},"C","项目仅进展到计划进度的91％",{"key":22,"text":23,"correct":24},"D","项目的每100元人民币投资中只创造相当于91元的价值",true,"成本执行（绩效）指数（Cost Performance Index．CPI）。CPI等于EV和AC的比值。CPI是最常用的成本效率指标。计算公式为：CPI=EV\u002FAC CPI值若小于1则表示实际成本超出预算，CPI值若大于1则表示实际成本低于预算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]