[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384087":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384087,165,1,"单选题","项目估算容易被忽略的主要因素不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","非直接成本",false,{"key":16,"text":17,"correct":14},"B","学习曲线",{"key":19,"text":20,"correct":14},"C","项目完成的时限",{"key":22,"text":23,"correct":24},"D","质量体系",true,"本题考查项目成本估算的主要相关因素。 除项目直接成本外，项目估算还需要考虑但容易被忽略的主要因素有以下几种：非直接成本；学习曲线；项目完成的时限；质量要求；储备。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]