[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384078,165,1,"单选题","关于项目进度管理中的活动历时估算的叙述，（ ）是正确的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","活动历时估算应给出尽量准确的结果，不应给出变化范围，例如. 2周±2天",false,{"key":16,"text":17,"correct":14},"B","多方案分析法是一种常用的活动历时估算方法",{"key":19,"text":20,"correct":21},"C","常用的活动历时估算方法包括类比估算、参数估算、三点估算法和后备分析法",true,{"key":23,"text":24,"correct":14},"D","类比估算法也称为自下而上估算法，常用于项目早期的活动历时估算","A说反了，活动历时估算应指明变化范围。B：活动历时估算方法没有多方案分析法。D：应为自上而下",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]