[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384076":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384076,165,1,"单选题","前导图和箭线图都是网络图。它们之间的主要差别是：（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","箭线图在活动期间与PERT图合并",false,{"key":16,"text":17,"correct":18},"B","前导图将活动作为节点",true,{"key":20,"text":21,"correct":14},"C","箭线图不能指明关键路径",{"key":23,"text":24,"correct":14},"D","前导图将浮动时间作为活动历时的一部分","前导图将活动作为节点。两个图形方法都显示项目活动的逻辑关系。箭线图用箭线代表活动。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]