[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384074":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384074,165,1,"单选题","项目进度表至少包括每项计划活动的计划开始日期与计划完成日期，常见的做法是用一种或多种格式的图形表示。在下面的图表中，常用于表示项目进度表的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图",true,{"key":16,"text":17,"correct":18},"B","排列图",false,{"key":20,"text":21,"correct":18},"C","鱼骨图",{"key":23,"text":24,"correct":18},"D","趋势图","横道图用横道表示活动，注明了活动的开始与结束日期，以及活动的预期持续时间。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]