[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384072":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384072,165,1,"单选题","三点估算中，PERT使用的3种估算值有最乐观时间、最悲观时间和（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最可能时间",true,{"key":16,"text":17,"correct":18},"B","最长时间",false,{"key":20,"text":21,"correct":18},"C","最短时间",{"key":23,"text":24,"correct":18},"D","最保守时间","本题考查PERT使用的3种估算值。PERT使用的3种估算值有最可能时间、最乐观时间、最悲观时间。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]