[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384069":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384069,165,1,"单选题","关于定义活动的输入错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目进度管理计划中规定了管理项目工作所需的细致程度。",false,{"key":16,"text":17,"correct":14},"B","在定义活动时，需明确考虑范围基准中的WBS、可交付成果、制约因素和假设条件。",{"key":19,"text":20,"correct":14},"C","能够影响定义活动过程的组织过程资产包括标准化的流程。",{"key":22,"text":23,"correct":24},"D","会影响定义活动过程的事业环境因素不包括项目管理信息系统。",true,"本题考查定义活动的输入。会影响定义活动过程的事业环境因素包括：组织文化和结构；商业数据库中发布的商业信息；项目管理信息系统。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]