[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384067":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384067,165,1,"单选题","关于估算活动持续时间的输入说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","估算的活动资源需求会对活动持续时间产生影响。",false,{"key":16,"text":17,"correct":14},"B","资源日历中的资源可用性、资源类型和资源性质，都会影响活动的持续时间。",{"key":19,"text":20,"correct":14},"C","在估算活动持续时间时，需要考虑项目范围说明书中所列的假设条件和制约因素。",{"key":22,"text":23,"correct":24},"D","风险登记册只提供风险清单，不会对风险分析和应对规划提供结果。",true,"本题考查估算活动持续时间的输入。风险登记册只提供风险清单，以及风险分析和应对规划的结果。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]