[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384066,165,1,"单选题","关于控制进度的输入说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度基准用于判断是否需要进行变更、采取纠正措施或采取预防措施。",false,{"key":16,"text":17,"correct":18},"B","关于项目进展情况的信息是项目日历。",true,{"key":20,"text":21,"correct":14},"C","在控制进度过程中需要对进度数据进行审查和更新。",{"key":23,"text":24,"correct":14},"D","会影响控制进度过程的组织过程资产包括进度控制工具、可用的监督和报告方法。","本题考查控制进度的输入的相关信息。工作绩效数据是是关于项目进展情况的信息。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]