[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384062":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384062,165,1,"单选题","在项目实施过程中，项目经理通过项目周报中的项目进度分析图表发现机房施工进度有延期风险。项目经理立即组织相关人员进行分析，下达了关于改进措施的书面指令。该指令属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","检查措施",false,{"key":16,"text":17,"correct":14},"B","缺陷补救措施",{"key":19,"text":20,"correct":21},"C","预防措施",true,{"key":23,"text":24,"correct":14},"D","纠正措施","预防措施是为降低项目风险的可能性而提出的建议文件。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]