[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384058":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384058,165,1,"单选题","范围控制的目的是监控项目的状态，如“项目的工作范围状态和产品范围状态”，范围控制不涉及（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","影响导致范围变更的因素",false,{"key":16,"text":17,"correct":14},"B","确保所有被请求的变更按照项目整体变更控制过程处理",{"key":19,"text":20,"correct":14},"C","范围变更发生时管理实际的变更",{"key":22,"text":23,"correct":24},"D","确定范围变更是否已经发生",true,"范围控制涉及到以下内容：影响范围变更的因素，确保所有被请求的变更按照项目整体变更控制处理，范围变更发生时管理实际的变更。范围控制与其他控制过程完全结合。未控制的变更经常被看作范围溢出。变更应当被视作不可避免的，因此要颁布一些类型的变更控制过程。可见范围控制不涉及D。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]