[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384055,165,1,"单选题","以下关于项目范围控制与用户需求变更的联系说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","用户的需求变更必须控制在可控范围之内。",false,{"key":16,"text":17,"correct":14},"B","如果项目团队缺乏明确的需求变更管理控制及范围管理控制，非常容易导致项目的失控。",{"key":19,"text":20,"correct":14},"C","需求基线定义了项目的范围。",{"key":22,"text":23,"correct":24},"D","需求基线是固定的，不需要根据少量需求变更而改变。",true,"本题考查项目范围控制与用户需求变更的联系。 每次需求变更并经过需求评审后，都要重新确定新的需求基线。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]