[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384052,165,1,"单选题","某项目工期为一年，项目经理对负责项目工作分解结构编制的小张提出了如下要求或建议，其中（ ）是不妥当的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应该在2周内把全年工作都分解到具体工作包",true,{"key":16,"text":17,"correct":18},"B","可根据项目生命周期的阶段进行第一层分解，而把可交付物安排在第二层",false,{"key":20,"text":21,"correct":18},"C","可考虑以一个人80小时能完成的工作作为一个工作包",{"key":23,"text":24,"correct":18},"D","可采用树形结构和列表形式相结合的方式进行分解","工作分解结构WBS两周法则法则是指工作包的工作量，并不是指两周内完全分完，而且工期为一年，跨度比较大，不可能应该在2周内把全年工作都分解到具体工作包，这样和滚动式的分解做法是相悖的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]