[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384047":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384047,165,1,"单选题","在系统建设后期，建设方考虑到系统运维管理问题，希望增加8课时的IT服务管理方面的知识培训，承建方依此要求进行了范围变更。在对范围变更进行验证时，验证准则是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","学员签到表",false,{"key":16,"text":17,"correct":14},"B","安排一次考试，以测验分数",{"key":19,"text":20,"correct":21},"C","新批准的培训工作方案",true,{"key":23,"text":24,"correct":14},"D","培训范围变更请求","此题关键在于对“对范围变更进行验证”这句话的理解，由于该范围变更的结果为新的培训方案，因此，验证这个变更的准则就是新的培训方案。可以这样理解：1、范围控制，2、变更请求（范围控制的输出），3、进行范围变更，4、输出——产生新的培训方案。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]