[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384024":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384024,165,1,"单选题","结束项目或阶段的输出包括最终产品、服务或输出移交和组织过程资产更新，下列不属于组织过程资产更新的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目档案",false,{"key":16,"text":17,"correct":18},"B","项目审计",true,{"key":20,"text":21,"correct":14},"C","项目或阶段收尾文件",{"key":23,"text":24,"correct":14},"D","历史信息","本题考查组织过程资产更新。 组织过程资产更新包括：项目档案、项目或阶段收尾文件、历史信息。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]