[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384023":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384023,165,1,"单选题","项目进行过程中，客户要求进度提前，围绕整体变更管理，项目经理以下做法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度变更和整体变更应一步到位，不要反复迭代",false,{"key":16,"text":17,"correct":14},"B","进度变更对成本、人力资源的影响，可在变更实施时再进行评价",{"key":19,"text":20,"correct":21},"C","先要求提出变更申请，走进度变更流程，然后根据变更后的新基线再进行相关的成本、人力资源等的变更",true,{"key":23,"text":24,"correct":14},"D","只要变更内容正确，即可执行变更","要从整体管理的角度看待每一项变更申请；要掌握规范的变更流程。在项目管理过程中，所有变更多必须走变更控制流程：（1）受理变更申请（2）对变更进行审核（3）变更方案论证（4）提交上级部门（变更管理委员会）审查批准（5）实施变更（6）对变更的实施进行监控（7）对变更效果评估",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]