[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384022,165,1,"单选题","变更请求是监控项目工作输出的一部分内容，则下面不属于变更的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","纠正措施",false,{"key":16,"text":17,"correct":14},"B","预防措施",{"key":19,"text":20,"correct":21},"C","修正措施",true,{"key":23,"text":24,"correct":14},"D","缺陷补救","本题考查变更的内容。 变更至少包括：纠正措施、预防措施、缺陷补救。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]