[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384021":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384021,165,1,"单选题","以下各项中，（ ）不是整体变更控制的输入。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","己批准的纠正措施",true,{"key":16,"text":17,"correct":18},"B","己完成的可交付物",false,{"key":20,"text":21,"correct":18},"C","实际的绩效数据",{"key":23,"text":24,"correct":18},"D","己批准的项目管理计划","整体变更控制依据已批准的项目管理计划（也就是项目的基准计划）、变更申请、项目绩效和已完成的可交付物来进行。依据《系统集成项目管理工程师教程》的相关内容，“已批准的纠正措施”不是整体变更控制的输入。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]