[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384001":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384001,165,1,"单选题","有关可行性研究的叙述中错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","信息系统项目开发的可行性研究要从可能性、效益性和必要性入手",false,{"key":16,"text":17,"correct":14},"B","可行性研究要遵守科学性和客观性原则",{"key":19,"text":20,"correct":21},"C","信息系统项目的可行性研究，应对项目采用的技术、所处的环境进行全面的评价",true,{"key":23,"text":24,"correct":14},"D","项目可行性研究可采用投资估算法、增量净效益法等方法","可行性研究不仅要在技术和所处环境进行评价还包括其他方面",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]